Goals Achieved

  • Code was reorganized and structured for easy testing.
  • Made progress on the Note Selection window.

There won't be a preview this week. Not much has changed in the user side.

Problems

  • I had some university pressure this week which impacted my progress a little. I also was delayed as I was testing several autocomplete libraries. However, I should still be on schedule.

Next week

  • Investigate the possibility of exposing Joplin's Select window in order to standardize it.
  • Finish off the note select window along with its unit tests.
  • Change to use html-entities library for escaping.
  • If time allows, start work on Save behavior.